Nordex SE

Identify and resolve bottle- necks early with Meisterplan.

Make the right project portfolio decisions

Since 1985, Nordex SE has been pioneering the use of wind energy. Thanks to nearly three decades of experience, the com- pany is well positioned to handle an increasingly challenging regulatory environment and competitive industry. That is why it is as important as ever for Nordex SE to focus on their main goal – to develop plants that produce electricity at the same cost as conventional power plants.

CHALLENGE

With more than 2,500 employees and consolidated sales of about 1.43 billion euros in 2013, Nordex SE is among the top 10 companies in the wind power plant construction business. Due to a rising number of projects, the need for professional management of IT resources and projects increased in 2013.

Screen Shot 2018 12 06 at 22.04.12
Meisterplan opened our eyes to resource constraints.
- Felix Willing, PhD, CIO, Nordex SE

SOLUTION

After evaluating a number of project portfolio management solutions, Felix Willing, PhD, CIO of Nordex SE, chose Meisterplan, the dynamic PPM solution from itdesign GmbH. With this interactive and powerful PPM soft- ware, the IT department was able to quickly create a project portfolio based on their existing data. The tool’s simulation and analysis capabilities helped to make the right project and resource decisions.

Screen Shot 2018 12 06 at 22.04.25

BENEFITS

The new tool fits well into both the IT department as well as in the field. It answers the two most important questions of Willing’s team: Where are the bottlenecks in the project portfolio and how can they be resolved? Willing sums it up for his organization:“Meisterplan is an eye-opener.“

IT DEPARTMENT AS THE INTERFACE AND “HEART“ OF AN ENGINEERING COMPANY

Nordex has consistently aligned itself with this goal in recent years. To achieve this, management has implemented a bundle of new strategies:

  • the development of cheaper facilities with intelligent solutions in less windy areas
  • the reduction of production costs and general operating costs
  • the initiation of operational excellence programs
  • the focus on technical advantages and how to exploit them when positioning itself againstcompetitor’s promises in the industry.Nordex’s IT division is a key componet in many of its activity and program packages. IT is central to achieving ambitious business goals, sound processes, transparent interfaces and efficient project and portfolio management. In order to ensure perfect collaboration, a company must have a solid project portfolio management (PPM).

This is where decisions are made regarding which planned projects are really carried out now and at what cost. It is also where the determination of sufficient resources and time to engage the envisioned project portfolio takes place – and whether, or to what extent the projected outcome of the portfolio will meet the overall goals of the company.

THE KEY INGREDIENT TO SUCCESSFUL PPM — PROPERLY IMPLEMENTING THE RIGHT PROJECTS

A Project Management Office (PMO) has taken over the task of managing the IT project portfolio. To do this, the PMO uses specific software solutions. At Nordex, a PPM committee of IT executives is in charge of this responsibility. PPM is a key focus of Felix Willing, PhD, CIO of Nordex SE since 2012. Prior to his arrival, too many scheduled IT projects were neither selected nor prioritized, but were more or less implemented ad hoc as required by the requesting departments.

“It was obvious that we would not reach the future requirements of the holding company with such an approach,“ reflects Willing upon the situation at that time. “As an essential lever, we focused on project portfolio management and applied that first,“ Willing continues.

In addition to the great challenge to create a coherent project portfolio from the large number of IT projects, the entire IT division suffered from staff shortages. This was in spite of established project management and possessing detailed project data.

“The well-designed approaches failed in practice due to the great expense needed to integrate new projects or the inherent differences in project applications and organizational details.“

Unfortunately, an overview of the entire portfolio was missing. Resources were not utilized optimally and projects could not be planned transparently.

In their search for a solution, Willing’s team evaluated various options — including the use of complex, enterprise-wide project management soft- ware.However,theteamdidnotpursuethisbecause of the effort involved. Willing explains:

“The well-designed approaches failed in practice due to the great expense needed to integrate new projects or the inherent differences in project applications and organizational details.“ The ques- tion of how to realize transition from professional IT project management to an equally professional and successful project portfolio management in IT still remained. In 2013, the Nordex IT division ventured a second attempt to answer this question.

Creating a coherent portfolio out of many projects

Nordex’s IT department introduced a new portfolio process which incorporates itdesign’s PPM solution Meisterplan at a crucial point. Today, the new PPM process is comprised of only a few steps. For Nordex, the following three aspects were of particular importance when choosing Meisterplan:

  1. the simple transfer of data from various sources, in this case MS SharePoint and MS Excel,
  2. the intuitive possibilities for simulation of different scenarios and
  3. the significant, intuitive management reports. With a few clicks, they are created quickly for the decision-making bodies.
Today, within minutes, we are able to get an overview of our project portfolio with interactive analysis capabilities

These three key functionalities of Meisterplan were integrated into Nordex’s portfolio planning with minimal implementation effort. The imported project portfolio can now be displayed according to company-specific ranking. With much less time and effort, a transparent and weighted project portfolio of Nordex IT was created.

SAFE, FAST AND TRANSPARENT: MAKE THE RIGHT PROJECT PORTFOLIO DECISIONS

Meisterplan helps the decision makers at Nordex get a clear overview of project costs and the interdepartmental employee workloads. Via the graphical user interface, members of the PPM

committee are able to simply simulate possible planning alternatives with a few clicks. They can compare and select different plans using the scenario functionality. While planning, the results of adjustments to projects and resources are visible interactively. Thus, precise portfolio plans can be created and comprehended. After the committee selects the right strategic plans, they can easily convert them into their existing reporting structures or display them via integrated Meisterplan reporting.

“Today our IT department is equipped better than ever to do our part to achieve the business goals.”

PROJECT PORTFOLIO MANAGEMENT WITH MEISTERPLAN: FAST. INTERACTIVE. TRANSPARENT. TO THE POINT.

Willing considers Meisterplan to be the ideal solution for executing professional project port- folio planning: “We intensively studied a variety of approaches and concepts for PPM. Meisterplan was very attractive with its slight learning curve and short implementation time. Our first project portfolio plan using our data within MS SharePoint was available within a few weeks. Meisterplan was seamlessly integrated into the IT planning process at Nordex.“

However, quick and easy implementation is only one of the advantages. According to Willing, “The decisive factor is that Meisterplan gives us a powerful tool for project prioritization and analysis. We now have an overview of our entire project

portfolio within minutes, and with interactive analysis included! IT departments often have complex project dependencies and resource constraints.Nowwithaglance,wecanpinpointour portfolio weaknesses. Best of all, we are able to simulate various scenarios and prioritization when presenting portfolio decisions to the board.”

Employee well-being has greatly benefited from the adoption of Meisterplan. “A well-planned project portfolio can prevent bottlenecks early on. My employees seldom work past their limits which ensures good project results. Meisterplan quickly answers the most important question: Where are the portfolio constraints and how can we resolve them?” Willing easily sums it up: “Meisterplan is an eye-opener.“